An acquisition closing checklist should distinguish agreement from readiness. A supported finding can inform a proposal. Negotiation can establish terms. Neither event proves that the documents, permissions, funding, and other requirements for completion have been addressed.

The buyer's practical task is to keep that chain visible: finding, decision, document, evidence, and responsible person. The checklist is an organizing tool for the transaction team. It does not replace counsel's assessment, authorize a payment, or certify that a transaction is ready to close.

This article accompanies Module 6: Purchase agreement & close, the final lesson in the six-part Acquisition Playbook. It brings Cedar Workshop's fictional diligence findings into documentation and closing readiness, then separates the short operating handover from obligations that may continue afterward.

Carry the finding through to the agreement

Cedar's earnings review supports $40,000 of a proposed $120,000 consulting adjustment. Added to reported EBITDA of $1 million, that produces $1.04 million before other checks. Module 5 applies an illustrative 5x multiple to show a $5.2 million calculation, not an agreed purchase price.

The next record must distinguish what happened in negotiation from the buyer's preferred response. If the parties agree a price or another commercial treatment, their advisers need to connect it to the appropriate documents and calculations. A findings report does not amend an agreement simply by existing.

Use a row for each material issue. For the consulting adjustment, record the evidence, the buyer's position, any accepted outcome, and the relevant document reference. For premises permission, keep the unresolved requirement visible. For owner responsibilities, connect the operating plan to any agreed support. Different findings require different decisions.

Read closing economics as separate components

The agreed headline price need not equal the cash transferred at completion. The agreement may specify adjustments, deferred payments, conditional payments, or other components. The definitions and calculation rules matter more than an informal label on the proposal.

Working capital in a transaction is defined by the agreement for its particular purpose. A working-capital target, sometimes called a peg, is an agreed benchmark. BDO's working-capital analysis explains the importance of defined inclusions, exclusions, and measurement rules when comparing the delivered amount with the target.

For a separate hypothetical example, assume a $500,000 agreed target, $450,000 delivered under the same agreed definitions, and an expressly agreed dollar-for-dollar downward adjustment for a shortfall. Under those assumptions, the adjustment is $50,000 downward.

Hypothetical calculationAmount
Agreed target$500,000
Delivered working capital$450,000
Shortfall$50,000
Downward adjustment under the assumed mechanism$50,000

This is not an earnings adjustment. Do not apply the 5x earnings multiple to the shortfall. The example also does not supply enough information to calculate a total closing payment. A different agreement can use different definitions and mechanisms, so the actual documents and adviser review remain essential.

Distinguish signing from closing

Signing means executing the purchase agreement. Closing means completing the purchase under its terms and applicable requirements. These can happen together or at different times. A signed purchase agreement can create enforceable obligations before completion; it is not equivalent to a preliminary proposal whose main commercial terms are intended to be non-binding.

When signing and closing are separated, the documents can address interim commitments and requirements for completion. DLA Piper's purchase-agreement overview describes conditions and closing deliveries. Its specific regulatory examples concern their stated jurisdiction; they are not a universal checklist.

For the buyer, the useful question is what must occur next under this agreement. Do not assume there is a universal deadline, an unrestricted right to withdraw, or permission to operate the business before completion. Counsel should explain the actual commitments and available options.

Turn each pre-closing requirement into an evidence question

Cedar's building is not included in the proposed acquisition, and required premises permission remains missing in the teaching example. A lower price does not obtain that permission. A signed agreement and prepared funds do not resolve it either. Counsel must assess its legal and contractual treatment.

The tracker needs more than “lease received.” It should identify the relevant requirement, the person responsible for addressing it, the due point, the evidence needed, and the current status. The answer might require a document, approval, confirmation, or further professional assessment. Record what the actual process requires, not what would make the board easier to clear.

The same logic applies to funding. A preliminary funding proposal is not the same as satisfying all funding conditions or having funds available under the completion arrangements. Track the actual evidence and responsible parties. Keep funding, permissions, final documents, signatory authority, and required deliveries distinct so that one completed item cannot hide another missing one.

Use two lists, not one closing-day list

The first list covers pre-closing requirements. These are matters that need to be addressed for completion under the agreement and applicable law. The second covers post-closing responsibilities: obligations or operating tasks that genuinely belong after completion.

Examples of post-closing obligations can include a final adjustment process, repayment under an agreed seller note, or reporting for an earn-out. Include only the obligations that actually apply, with their document references, deadlines, and responsible people. For working capital, BDO's discussion of agreement definitions explains why the calculation method should be clear to both parties.

Do not move a missing pre-closing approval into the second list merely because the planned completion date is close. Relabeling the task does not change the requirement. Any proposed change in treatment requires the appropriate assessment and agreement; the tracker does not grant authority to waive or postpone it.

Hand-drawn illustration of the diligence evidence underlying closing decisions

Closing readiness depends on the evidence for the actual requirements, not the number of completed rows.

Prepare the day-one handover before it is needed

Planning can begin before closing within the agreed confidentiality and access arrangements. Taking control should not be assumed before completion. Keep proposed responsibilities labeled as proposed until the relevant people have accepted them and any necessary arrangements are in place.

For Cedar, the immediate operating questions concern customer relationships, quotation work, and production oversight. Who handles each task? What information or training is needed? When is support available? What happens if the intended person is unavailable? A general promise that the owner will “help with transition” does not answer those questions.

The handover should also cover people, premises, systems access, payroll, and operating cash. Start with continuity, then compare early results with the assumptions behind the acquisition. A long improvement agenda is less useful on day one than knowing who can authorize payroll and keep existing customer commitments moving.

Test the checklist with one unresolved fact

Suppose the agreement is signed and funds are prepared, but required premises permission is still missing. Is Cedar ready to close? The available facts do not establish readiness. The transaction team needs counsel's assessment of the outstanding requirement and available options.

That test reveals whether the checklist is recording evidence or merely activity. “Document drafted,” “email sent,” and “meeting held” describe work performed. They do not necessarily establish that the requirement was satisfied. Keep the completed action and the remaining question in the same row until there is a supported disposition.

Before the final readiness review, check that material findings have an agreed or explicitly unresolved response, calculations follow the documents, required evidence is attached, and continuing obligations have owners. The actual transaction may require additional specialist work. No generic checklist can establish the complete legal requirements of every acquisition.

Finish the playbook with one connected record

Module 1 defined fit. Module 2 identified the questions worth asking. Module 3 tested early answers. Module 4 developed deeper findings. Module 5 connected those findings to a proposal. Module 6 follows the agreed decisions into completion and handover.

Watch Module 6 and use its closing-and-handover worksheet. Keep pre-closing requirements and post-closing responsibilities separate, while preserving the evidence that connects them to the same acquisition. The full playbook is available whenever an earlier assumption needs to be revisited.

General buyer-side education. This is not legal, accounting, tax, valuation, financing, or investment advice, and it is not a closing authorization. Transaction-specific decisions require qualified advisers.